Second Crew will finish decommissioning the last well on North St, followed by the installation of 3 more wells between Cedar and Atlantic, they will also continue to set up the dewatering system along Bay Avenue throughout the week.
As of right now, National Watermain is scheduled to come in next Saturday April 6th, to grout the laterals between Ocean Ave and Gravelly Point Rd. Carroccia Paving is tentatively scheduled for the week of April 8th to begin the mill and overlay work on Ralph and Williams st.
Monmouth County, please be advised that Roman E&G plans to have detours/work being set up and performed on the county roads from April 1st on. I will be in touch with the county if anything were to change in that regard.