The County is slightly delayed in their paving schedule. We will have an update on Monday as to when they will start in Highlands. Please…
Carroccia’s milling machine is still being worked on after it went down last week, the part needed is coming in today so they will be…
Road Reconstruction will begin on Ocean Ave on Tuesday 10/15. Carroccia will not be on-site today, 10/14.
Plan is to begin milling, grading, and asphalting Ocean Ave on 10/14, followed by the 2″ top coat on all of the municipal roads during…
Update: Today’s excavation on Beach Blvd is now beginning tomorrow, Tuesday, 10/8.
Plan is to begin milling, grading, and asphalting Beach Blvd the week of 10/7, followed by Ocean Ave the week of 10/14.
Carroccia will be mobilizing and beginning work on Thursday 10/3.
Carroccia is scheduled to begin the excavation and sub-base work on Central Ave on Wednesday 10/2, as the weather for the beginning of the week…