Carroccia’s milling machine is still being worked on after it went down last week, the part needed is coming in today so they will be on-site starting on Wednesday 10/16.
Roman understands the urgency of the town and Carroccia is on board with the schedule to be done ahead of the County paving that will be on 10/22.
Schedule is as followed:
Wednesday 10/16- Friday 10/18: Ocean Ave Reconstruction
Monday 10/21: Top Course on all 3 streets