2 week look ahead and traffic detour plan for the Phase 1 Sanitary Sewer Job in Highlands.
One crew will be working doing laterals on the upper half of Linden Avenue, from school driveway up to 36, starting on Tuesday next week.
Second Crew will continue to test along Bay Avenue at the start of the week and then will transition to working with the decommissioning crew towards the end of the week.
Decommissioning Crew will be on-site Thursday of next week, Maintenance needs to be completed on the rig between Tuesday and Wednesday of next week. Plan for Decommissioning is:
-Beach
-Central
-Bay (Ocean to Snug Harbor)
-Ocean
-Bay County