Mainline will be working between Kay and Shrewsbury Ave. the week of 8/28. The following week, starting the Tuesday after the holiday, Mainline crew will be working at the intersection of Shrewsbury Ave. to Shore Dr.
New England Dewatering will be back on-site on or about 8/31 to begin decommissioning wells on Central, Ocean and Beach on 9/5.
Bay Ave. (49, 60, 78 Bay and Shrewsbury intersection): August 28 – September 7
Central/Beach/Ocean: August 31 – September 7