2 week look ahead and traffic detour plan for the Phase 1 Sanitary Sewer Job in Highlands.
Mainline crew will continue to install Main & Manholes on the local portion of Waterwitch Ave for the next couple of weeks.
Testing Crew will finish testing the remaining sections on Bay Avenue and then North St before shifting to finishing the laterals on Waterwitch between Recreation and Marine Pl, and then digging Test Pits along the remaining sections of Bay Avenue.