Phase 1 Sanitary Sewer Job Update

Please see the attached 2 week look ahead and traffic detour plan for the Phase 1 Sanitary Sewer Job in Highlands.

Mainline crew will begin the week working on test pits and laterals along Bay Avenue, before shifting to installing 12″ PVC Main along Bay Avenue towards the middle of the week.

Second Crew will begin the week decommissioning the last couple of wells that need to be removed, followed by storm drain work towards the end of the week.

Roman E&G posting crew is on vacation this week so there will be no fliers posted to the businesses and the homes along Bay Avenue​​​ 

Please have the residents notified through an alternate means for just this one week (Bay Ave from Cornwall to Atlantic)