Roman E&G crew will be finishing up demobilization in the beginning of the week.
Carroccia Concrete Crew will be on-site Monday and Tuesday (7/15 & 7/16) to finish the stamped concrete work along Bay Ave (Miller to Shrewsbury)
Carroccia Asphalt Crew will be on-site Tuesday to begin the mill and overlay work on the local section of Waterwitch. Roman E&G handed out fliers this morning to alert the residents all along Waterwitch.