2 week look ahead for the Phase 1 Sanitary Sewer Plan in Highlands

Plan is to finish pouring the sidewalk on Ocean Ave between Monday and Tuesday and then finish the ADA Ramps on Waterwitch (Local).

Carroccia is tentatively scheduled to begin the asphalt work on Central the week of the 23rd.