Update: Traffic Detour Plan

2 week look ahead and traffic detour plan for the Phase 1 Sanitary Sewer Job in Highlands.

Roman E&G has a company wide New Year Safety Kick-off Meeting on Tuesday, January 2nd, as a result we will not be working that day.

One crew will continue installing laterals on the upper half of Linden Avenue, from school driveway up to 36, starting on Wednesday next week (January 3rd).

Second Crew will transition to working with the decommissioning crew starting on Wednesday, along with continuing to test the newly installed sewer.

Plan for Decommissioning is:

-Beach

-Central

-Bay (Ocean to Snug Harbor)

-Ocean

-Bay County