Menu Close

Sanitary Sewer Work Schedule: 8/14 – 8/25

Mainline crew will be installing pipe between North and Jackson for the week of 8/7 and then working between Jackson and Spring St. the following week 8/14.

Cornwall: August 14

Bay Ave.: August 14 – 24

Jackson: August 16 – 17

Spring: August 22

Central/Beach/Ocean: August 21 – 24

Sign up for Nixle to get alerts.