Mainline Crew will finish their work on Tuesday on North St, completing the tie-in at Bay Avenue and then they will start on Bay Avenue on or about Wednesday, August 2nd. The following week (8/7) we will continue Bay Avenue heading towards the bridge with mainline sewer pipe.
North St.: July 31 – August 1
Bay Ave.: August 1 – 10
Cornwall: August 3
Jackson: August 9