Phase 1 Sanitary Sewer 2 Week Look Ahead

Monday, February 19th, is a recognized union holiday so as a result there will be no work in Highlands on Monday.

Beginning on Tuesday, February 20th, mainline crew will continue to install Main & Manholes on the local portion of Waterwitch Ave.

Second Crew will begin test pitting along Bay Avenue starting between Atlantic and Cedar.