How to Obtain Inspections

How to Schedule Inspections

The Uniform Construction Code requires that all inspections be requested IN WRITING. You may schedule an inspection by emailing our Technical Assistant.You must provide the following information:

  • Work Address
  • Permit number
  • Discipline of Inspection
    • Building, Fire, Electric, Plumbing, Mechanical
  • Type of inspection requested
    • Rough, Trench, Framing, Final, etc.
  • Name of contact and phone number

Click here for REQUIRED INSPECTIONS

UCC inspections are conducted Monday through Friday during regular business hours and after hours, unless other special arrangements are made with a Subcode Official. If conditions are such that a specific time frame is needed, please contact the appropriate Subcode Official and accommodations will be made to the extent possible.

In accordance with N.J.A.C. 5:23-2.18(c), a request for inspection must be given at least 24 hours prior to the time the inspection is desired. All inspections will be performed within three business days of the time for which it was requested

Construction Permit Fees

Click here for Construction Permit Fees