The County is slightly delayed in their paving schedule. We will have an update on Monday as to when they will start in Highlands. Please…
Carroccia’s milling machine is still being worked on after it went down last week, the part needed is coming in today so they will be…
Road Reconstruction will begin on Ocean Ave on Tuesday 10/15. Carroccia will not be on-site today, 10/14.
Plan is to begin milling, grading, and asphalting Ocean Ave on 10/14, followed by the 2″ top coat on all of the municipal roads during…
Highlands Vulnerability Presentation_FINALDownload
Update: Today’s excavation on Beach Blvd is now beginning tomorrow, Tuesday, 10/8.
Join us in extending a helping hand to Lake Lure. Click to see how you can help.
Plan is to begin milling, grading, and asphalting Beach Blvd the week of 10/7, followed by Ocean Ave the week of 10/14.