Phase 1 Sanitary Sewer 2 Week Look Ahead
Carroccia's milling machine is still being worked on after it [...]
Carroccia's milling machine is still being worked on after it [...]
Road Reconstruction will begin on Ocean Ave on Tuesday 10/15. [...]
Plan is to begin milling, grading, and asphalting Ocean Ave [...]
Highlands Vulnerability Presentation_FINALDownload
Update: Today's excavation on Beach Blvd is now beginning tomorrow, [...]
Plan is to begin milling, grading, and asphalting Beach Blvd [...]
Carroccia will be mobilizing and beginning work on Thursday 10/3.
Carroccia is scheduled to begin the excavation and sub-base work [...]