One Crew will be working installing laterals along Bay Avenue between Huddy and Marine Bay for the next couple of weeks.
Second Crew will finish up isolating and testing on the municipal roads until the middle of next week and then shift to begin testing on Bay Avenue.
Well removal along Ocean, Beach, Central and Bay is scheduled to begin on or about December 18th.