Check out our daily construction progress. Click to view the worksite.
For information regarding project, please contact aloudin@settembrino.com.
- 2022 February 25 – New Municipal Building: Addendum 6
- 2022 February 17 – New Municipal Building: Addendum 5
- 2022 February 15 – New Municipal Building: Addendum 4
- 2022 February 11 – New Municipal Building: Addendum 3
- 2022 February 3 – New Municipal Building: Addendum 2
- 2022 February 2 – New Municipal Building: Addendum 1
- 2022 January – RFP for Construction Bids
- 2021 October – Target for putting work out to bid
- 2021 June – Appropriate $10 million for construction [O-21-28, $5 million FEMA reimbursement + $4,750,000 Bonds + $250,000 Borough funds]
- 2021 May – Zoom meeting with NJOEM, Architect, CFO, Administrator & Mayor
- 2020 September – Opened Borough parking lot at 171 Bay Avenue
- 2019 September – Special Meeting to discuss new building and other projects
- 2019 August – Demo 171 Bay Avenue
- 2019 June – Demo begins of convent and thrift shop
- 2018 December – Actual sale date when property transferred to the Borough
- 2018 October – Award Settembrino as Architect
- 2017 September – Sign contract for 181 Navesink Ave for $450,000
- 2016 May – Interview top 4 from score sheet
- 2016 April – Appropriate $3 million for preliminary work and property purchase [O-16-7, $1,200,000 FEMA reimbursement + $1,710,000 Bonds + $90,000 Borough funds]
- 2016 March – RFP of Architect
- 2015 – Full year spent on site search with FEMA input
- 2012 Oct – Hurricane Sandy